The HoSt Group has started construction of a 25 MW combined heat and power plant based on industrial waste wood in the Osnabrück region. The project makes a direct contribution to the industrial energy transition, as it completely replaces a pulverised lignite firing system and two gas boilers previously used by industrial customers. The plant, which is expected to be fully operational in mid-2027, serves as a strategic model for industrial heat and electricity consumers who want to phase out fossil fuels through reliable and cost-efficient renewable energy in the form of a contracting model.